Project 02 · $15M Brownfield Design-Build Expansion

Petrochemical Terminal Expansion

Role
Project Manager
Company
SCG
Location
Map Ta Phut, Rayong, Thailand
Period
2016-2019
NJ on site at the Petrochemical Terminal Expansion project
Project Value
~$15M
Cost Avoided
~$500K
Budget Protected
~$300K
Accidents
Zero

01 · Scope

Project context and delivery environment.

Design-Build expansion delivered inside an operating petrochemical terminal without a total terminal shutdown.

Client / Project Environment
Dow joint-venture petrochemical operation / Rayong Terminal
Project Value
Approximately $15M
Location
Map Ta Phut, Rayong, Thailand
Period
2016-2019
Delivery Model
Owner / Developer-side Design-Build
Major Scope
2 marine loading arms, 2 transfer pumps, 2 storage tanks, new pipe rack, existing substation revamp, associated piping, and terminal infrastructure

02 · Personal Contribution

What NJ personally owned and contributed.

These statements describe NJ's direct role within the wider project organization.

  1. 01

    Served as Owner-side Project Manager with end-to-end responsibility from technical assessment and scope definition through engineering, procurement, construction, commissioning, and operational handover.

  2. 02

    Developed project scope, technical requirements, procurement packages, project budget, master schedule, milestones, risk register, and execution strategy.

  3. 03

    Led RFQ/RFP development, technical and commercial bid evaluations, bid leveling, vendor negotiations, contract administration, and equipment procurement.

  4. 04

    Managed the engineering consultant and Design-Build engineering team, including constructability reviews and interfaces between new facilities and the operating terminal.

  5. 05

    Coordinated construction sequencing and system-by-system tie-ins so the expansion could be delivered without a total terminal shutdown.

  6. 06

    Managed contractor interfaces, schedule recovery, change orders, claims, project risks, permitting, regulatory requirements, and marine-installation constraints.

  7. 07

    Coordinated Mechanical Completion, punch-list closure, testing, commissioning, performance acceptance, documentation, and final operational handover.

  8. 08

    Reported scope, schedule, cost, risk, HSE, and key project decisions to management and the project steering committee.

03 · Outcome

Results delivered.

  • Delivered the approximately $15M project on schedule and on budget with zero accidents.
  • Avoided approximately $500K in excess project cost through technical-commercial bid evaluation and removal of over-specified scope.
  • Protected approximately $300K of project budget by evaluating and negotiating a $400K contractor claim down to approximately $100K.
  • Delivered the brownfield expansion through system-by-system integration without requiring a total terminal shutdown.
  • Protected a schedule-critical marine loading-arm installation window by coordinating permitting, engineering, contractors, Operations, port activities, vessel access, and tidal constraints.
Owner-Side Project ManagementDesign-BuildBrownfield ConstructionRFQ / RFPBid EvaluationChange Orders & ClaimsCommissioningOperational Handover